Invitation for Contract Awards Detail

GOVERNMENT OF THE PEOPLE'S REPUBLIC OF BANGLADESH

Ministry/Division : Ministry of Energy, Power and Minearal Resources
Agency : Northern Electricity Supply Company Ltd.
Procuring Entity Name : Project Director , Rangpur Division power distribution project, NESCO
Procuring Entity Code :
Procuring Entity District : Rajshahi
Contract Award for : Goods
Invitation/Proposal Reference No : 27.29.0000.015.07.233.22-2088; Date: 19/04/2022

KEY INFORMATION

Procurement Method : ICT
Tendering Method : One Stage & Two envelope Tendering Method

FUNDING INFORMATION

Budget and Source of Funds : Development Budget GOB
Development Partner (if applicable) : none

PARTICULAR INFORMATION

Project/Programme Name (if applicable) :
Tender/Proposal Package No : 73
Tender/Proposal Package Name : Procurement of Design, Supply, Installation, Testing and Commissioning of 02 nos 33/11KV, 2x10/13.33 MVA Regular Type New GIS Substation at Burimari, Patgram, Lalmonirhat & at Bhajanpur, Panchagarh on turnkey basis
Date of Advertisement : 20/04/2022
Date of Notification of Award : 18/10/2022
Date of Contract Signing : 08/11/2022
Proposed Date of Contract Completion : 08/11/2023
No. of Tenders/Proposals Sold : 8
No. of Tenders/Proposals Received : 5
No. of Tenders/Proposals Responsive : 4

INFORMATION ON AWARD

Brief Description of Contract : Procurement of Design, Supply, Installation, Testing and Commissioning of 02 nos 33/11KV, 2x10/13.33 MVA Regular Type New GIS Substation at Burimari, Patgram, Lalmonirhat & at Bhajanpur, Panchagarh on turnkey basis under Extension & Renovation Project of Distribution Line & Sub-Station for Rangpur Division, NESCO Ltd., Rangpur (ICT)
Contract Value : USD 35,65,660.00 (THIRTY FIVE LAKH SIXTY-FIVE THOUSAND SIX HUNDRED SIXTY US DOLLARS AND ZERO CENTS) + BDT 8,59,68,157.87 (EIGHT CRORE FIFTY-NINE LAKH SIXTY-EIGHT THOUSAND ONE HUNDRED AND FIFTY-SEVEN POINT EIGHT SEVEN TAKA)
Name of Supplier/Contractor/Consultant : Reverie Power & Automation Engineering Ltd.
Location of Supplier/Contractor/Consultant : Evergreen Plaza (5th & 7th floor), 260/B, Tejgaon I/A, Dhaka-1208
Location of Delivery/Works/Consultancy : Lalmonirhat
Is the Contract Signed with the same person stated in the NOA : Yes
If No give reason why :
Was the Performance Security provided in due time? : Yes
If No give reason why :
Was the Contract Singed in due time? : Yes
If No give reason why :

ENTITY DETAILS

Name of Authorised Officer : D.M. Abu Hena Mostafa Kamal
Designation of Authorised Officer : Project Director Extension and Renovation Project of Distribution Line and Sub-Station of Rangpur Division, NESCO PLC