Invitation for Contract Awards Detail
GOVERNMENT OF THE PEOPLE'S REPUBLIC OF BANGLADESH
Ministry/Division |
: |
Ministry of Water Resources |
Agency |
: |
Bangladesh Water Development Board (BWDB) |
Procuring Entity Name |
: |
Project Director, Coastal Embankment Improvement Project, Phase -1(CEIP-1), BWDB, Dhaka |
Procuring Entity Code |
: |
None |
Procuring Entity District |
: |
Dhaka |
Contract Award for |
: |
Services |
Invitation/Proposal Reference No |
: |
CEIP-1/S1-E/1988 dated 16-10-2018 |
KEY INFORMATION
|
Procurement Method |
: |
NCT |
Tendering Method |
: |
Consultants Qualifications Selection (CQS) |
FUNDING INFORMATION
|
Budget and Source of Funds |
: |
Development Budget Grant/Credit |
Development Partner (if applicable) |
: |
IDA ( World Bank) |
PARTICULAR INFORMATION
|
Project/Programme Name (if applicable) |
: |
|
Tender/Proposal Package No |
: |
CEIP-1/A2 & B1/S1-E |
Tender/Proposal Package Name |
: |
Non-Governmental Organization Services to implement a) Social Mobilization with Social Action Plan (incl. setting up WMOs); b)Social afforestation & c) Integrated Pest Management Plan for Polder No.43/2C, 47/2 & 48 |
Date of Advertisement |
: |
16/10/2018 |
Date of Notification of Award |
: |
30/04/2019 |
Date of Contract Signing |
: |
02/05/2019 |
Proposed Date of Contract Completion |
: |
30/06/2020 |
No. of Tenders/Proposals Sold |
: |
5 |
No. of Tenders/Proposals Received |
: |
4 |
No. of Tenders/Proposals Responsive |
: |
2 |
INFORMATION ON AWARD
|
Brief Description of Contract |
: |
The objectives of the consultancy services are to manage and oversee the tasks for social mobilization,participatory scheme cycle management (PSM) and participatory afforestation in relation to the successful implementation of the CEIP-1. Specially, the consultancy services was sought for a) Social mobilization including setting up WMOs for introduction of IWRM practices through preparation and implementation of Social Action Plan (SAP) through engagement of local communities and community groups for PSM and participatory O&M Schemes, b) Implementation of afforestation program, specially in the foreshore areas with ecologically appropriate species by adopting social afforestation approach , and c) Implementation of the Integrated Pest Management (IPM) practices for Polder No.43/2C, Polder No.47/2 and Polder No.48 in Patuakhali District. |
Contract Value |
: |
BDT 28,370,270.00 |
Name of Supplier/Contractor/Consultant |
: |
JV of Adarsha Manobseba Sangastha (AMS), Aid Organisation (AO) and People's Development Institute (PDI) |
Location of Supplier/Contractor/Consultant |
: |
Charpara, Patuakhali |
Location of Delivery/Works/Consultancy |
: |
Patuakhali |
Is the Contract Signed with the same person stated in the NOA |
: |
Yes |
If No give reason why |
: |
|
Was the Contract Singed in due time? |
: |
Yes |
If No give reason why |
: |
Not applicable |
ENTITY DETAILS
|
Name of Authorised Officer |
: |
Md. Habibur Rahman |
Designation of Authorised Officer |
: |
Chief Engineer & Project Director,
CEIP-1, BWDB, Dhaka |