Ministry/Division |
: |
Ministry of Road Transport and Bridges |
Agency |
: |
Roads & Highways Department (RHD) |
Procuring Entity Name |
: |
Construction Supervision Consultancy (CSC) Services for Rehabilitation of National Highway (N-1) Unchiprangto Teknaf(30.76km) |
Procuring Entity Code |
: |
N/A |
Procuring Entity District |
: |
Cox's Bazar |
Expression of Interest for Selection of |
: |
Consulting Firm (International) (Time-Based) |
Title Of Service |
: |
Construction Supervision Consultancy (CSC) Services for
Rehabilitation of National Highway (N-1) Unchiprangto Teknaf(30.76km)
|
EOI Ref. No. |
: |
35.01.2224.132....22/2788 |
Date |
: |
17/10/2022 |
KEY INFORMATION
|
Procurement Sub-Method |
: |
Quality and Cost Based Selection(QCBS) |
FUNDING INFORMATION
|
Budget and Source of Funds |
: |
Non_Development GOB |
Development Partners |
: |
N/A |
PARTICULAR INFORMATION
|
Project/Programme Name |
: |
Construction Supervision Consultancy (CSC) Services for Rehabilitation of National Highway (N-1) Unchiprangto Teknaf(30.76km) |
EOI Closing Date and Time |
: |
16/11/2022 4.00 pm
|
Publication Date |
: |
23/10/2022
|
INFORMATION FOR APPLICANT
|
Brief Description of Assignment |
: |
5. As part of the services the consultant will conduct the following works:
a) Planning, Reporting and Design review.
b) Procurement Assistance (If required)
c) Construction Supervision and Quality Control
d) Implementation Facilitation of Environmental Management Plan (EMP), Environmental Monitoring Plan (EMoP) and Resettlement Plan
e) Social Development, and Implementation of Safety and Traffic Management Plan
6. The above work includes the following tasks:
a) Planning, Reporting and Design Review
i) Prepare detailed work plan, implementation schedule and all progress reports (as required by ADB and RHD) for the project
ii) Review the detailed design done by RHD and update the design, if necessary during implementation period.
b) Procurement Assistance (If required)
i) Assist RHD in tendering stage, assist RHD during evaluation and in contract negotiation.
ii) Other procurement support as required for the project.
iii) Post procurement review or any required reporting.
c) Construction Supervision
i) Supervise all civil construction work and execute contract administration;
ii) Regularly monitor progress and take actions required for timely completion of works;
iii) Verify contractor’s work statements and issue payment certificates;
iv) Review and necessarily modify design, drawing, specification, cost etc.; and
v) Develop the quality assurance system and quality control plan for provisions of pavement and structures;
vi) Conduct all required tests (Laboratory tests/ Field Tests) and certify works.
vii) Prepare all progress reports, monitoring reports , compliance reports and other reports as required by RHD and ADB (Asian Development Bank)
d) Others
i) Facilitate the implementation of Environmental Management Plan (EMP), Environmental Monitoring Plan (EMoP) and Resettlement Plan;
ii) Prepare and facilitate implementation of a realistic traffic management plan;
iii) Review and facilitate implementation of Safety plan;
iv) Prepare environmental and social monitoring reports;
v) Preparation of Project Completion Report (PCR)
|
Experience, Resources and Delivery Capacity Required |
: |
a) Satisfactory completion of construction supervision at least 20 kilometer road section including flexible, rigid and semi-rigid pavement and PC Girder Bridge.
b) Detailed Design experience of 10 Km road section including flexible, rigid and semi-rigid pavement including culvert and PC Girder Bridge.
9. The EOI should specially include (along with certified English Translation if not in English);
a) The firm’s registration certificate;
b) Company profile: including management, personnel, firm’s specialty, performance;
c) List of completed services in last 10years for:
i. Detailed Design and /or Construction Supervision of 20.00 kilometer Road Projects
ii. Experience in road/bridge projects in Bangladesh;
iii. Experience in foreign-aided road/bridge projects in Bangladesh.
iv. Contracts where minimum 20 kilometer of road are designed/supervised and a PC Girder Bridge is included
In the above lists (i – iv) the following information should be provided:
Client’s name, nature of services, contract amount, man-months the firm extended, duration of the service with commencement and completion date;
d) Summary of permanent (At least one year)professional employees with key qualifications;
e) Number of Highway Engineers, Bridge Engineers and Quality Control Engineers those who belong to the firm more than a year and average working experiences (years) of those Engineers;
|
Other Details (if applicable) |
: |
|
Association with foreign firms is |
: |
Not Applicable |
Eoi Detail Information |
Ref No |
Phasing Of Services |
Location |
Start Date |
Completion Date |
1 |
N/A |
Dhaka |
N/A |
N/A |
|
PROCURING ENTITY DETAILS
|
Name of Official Inviting EOI |
: |
Mohammad Shahe Arefeen |
Designation of Official Inviting EOI |
: |
Executive Engineer, RHD |
Address of Official Inviting EOI |
: |
Cox’s Bazar Road Division,
Cox’s bazar
|
Contact details of Official Inviting EOI |
: |
Phone : 02334462460, Fax : , Email : arefeenrhd@gmail.com |
The procuring entity reserves the right to accept or reject all tenders |